BASIC PROJECT DATA
Project ID: PA1A159
Project website (German): http://www.schleuse-kriegenbrunn.wsv.de/
NEED AND ADDED VALUE FOR THE DANUBE REGION STRATEGY
The lock Kriegenbrunn was put into operation in 1972. Soon afterwards the first damages were discovered and first constructional rehabilitation measures were necessary in 1974. Until 2008, altogether five rehabilitation measures were needed in order to maintain the functionality of the lock, but the problems were not solved entirely.
OBJECTIVE(S) OF THE PROJECT
Building of the replacement construction.
The new lock will be built 45m downstream of the existing weir and lock. The lock chamber will have the same dimensions in lenght as the old lock (190m), while the width will be enhanced by 50cm to 12.5m.
As soon as the new lock has been put into operation, the existing lock will be shut down and partially dismantled.
CONDUCTED AND PLANNED PROJECT ACTIVITIES
The project will be implemented in 10 building phases, including the dismantling of the old lock.
- 2017: planning approval
- 2019 – 2024: construction works
- 2025: operation of the new lock
- 2027 – 2029: deconstruction of the old lock
TRANSBOUNDARY IMPACT
Since it is not possible to bypass the lock, its reconstruction is crucial for navigation along the entire Rhine-Main-Danube axis.
PROJECT BENEFICIARIES / TARGET GROUPS
waterway users
STATUS AND TIMEFRAME
Start date: 2015
End date: 2024
FINANCING
Total budget: approx. 210 million EUR entirely funded through national budget
PROJECT TEAM
Project leader: Wasserstraßen-Neubauamt Aschaffenburg / Germany
(website: www.wsv.de)
Address: Hockstraße 10, 63743 Aschaffenburg / Germany
There are no additional partners involved.
PROJECT ENVIRONMENT
PROJECT CROSS – REFERENCE
- Reconstruction of the Obernau lock (PA1A158)
- Reconstruction of the Erlangen lock (PA1A160)
EUSDR EMBEDDING
EUSDR COMPLIANCE
META DATA
Data provided by viadonau, based on information from the project website and the TEN-T Corridor Study for the Rhine-Danube Corridor – 25.09.2018
Download pdf